OUR TIMELINE
PURCHASING AND DECISIONS -
- December 31, 2012 - Sight unseen signed Purchase Agreement made first deposit and reserved Lot 10
- January 3, 2013 Met with NVR Mortgage - via phone
- January 20, 2013 Finalized Guardian - via phone/email
- January 27, 2013 Finalized Exceptional Choices - via phone/email
- January 31, 2013 Second Deposit
- February 27 - March 3, 2013 Fly from HI to VA for Pre-Con meeting
- February 28, 2013 Finally we walk through a Rome Model and meet our SR!
- February 28, 2013 Guardian Meeting at Rome Model
- March 1, 2013 Pre-Construction Meeting
- March 1, 2013 Final Deposit
- March 2, 2013 Met with Danni - Exceptional Flooring
- March 2, 2013 Paid for Red Flag Changes to add Stub out gas line - for back yard.
- May 20, 2013 Signed official Change of Address
The Build And Excitement Begins -
- May 24, 2013 - Permit finally in PMs hands!
- May 28, 2013 - Lot Staked
- May 31, 2013 - Broke Ground
- June 4, 2013 - Footings
- June 5, 2013 - Foundation and basement walls
- June 6-7, 2013 - Water Proofing and inspection
- June 10-12, 2013 - City Water/Sewage
- June 18-25, 2013 - Framing
- June 25-28, 2013 - Roofing, Fireplace and Windows
- July 1 - 10, 2013 - HVAC rough-ins
- July 1 - 8, 2013 - Plumbing rough-ins
- July 1 - 10, 2013 - Gas Line and Inspection
- July 1 - 10, 2013 - Electrical rough-ins
- July 1 - 10, 2013 - Low voltage wiring (Guardian)
- July 10, 2013 - 1030 Pre-Drywall Meeting
- Energy Inspection
- Insulation
Drywall to Closing:
- July 15-19 2013- Drywall
- July 19-20 2013 - Exterior siding, trim
- July 19 Priming walls
- July 25, 2013 - Locked in Interest Rate
- July 26, 2013 - all contingent mortgage loan documents submitted
- July 20-29, 2013 Painting
- July 20-29, 2013 Interior trim and cabinets
- July 29, 2013 - Driveway
- July 29- Aug 3, 2013 - Granite, ceramic tile, vinyl floors
- August 3-4 2013 - Hardwood flooring
- July 29, 2013 - electrical/Guardian hook up
- Aug 09, 2013 - Trimming out/finishing plumbing - fixtures, mechanical
- August 09, 2013 - Exterior stone, Fireplace stone
- August 09, 2013 - Appliances
- August 09,2013 - Carpet
- Cleaning
- Landscaping
- Final inspections, surveys.
- Scheduled 1000 August 21, 2013 - Pre-settlement Walk thru
- Scheduled 1300 August 23, 2013 - Original Close Date...Delayed
- Scheduled Time1300-1400 Day; August 27, 2013 Closing - A LOT of Papers signed - Keys in Hand!